Glossary
UK construction glossary
Practical definitions of the commercial, project-controls, and contractual terms UK construction consultancies use every week. Written for QSs, PMs, and directors — not for someone learning the industry.
C
Compensation Event
NECA compensation event is the NEC-contract equivalent of a variation — a defined event entitling the contractor to additional cost, time, or both, processed through a structured notification-and-quotation system.
Contingency
Contingency is a cost reserve held in the project budget to cover risks that may materialise during the project. UK consultancies typically distinguish design contingency, construction contingency, and employer's contingency.
Cost Plan
A cost plan is the consultancy's structured estimate of project cost, developed and refined through the design stages. It sits at the heart of pre-construction commercial work, evolving from order-of-magnitude at Stage 0 to detailed at Stage 4.
P
PCSR
Project Cost Summary ReportA PCSR — Project Cost Summary Report — is the monthly cost report at the heart of how UK construction consultancies report on project commercial position. Committed, anticipated, forecast, and out-turn cost, summarised by package.
Practical Completion
PCPractical Completion (PC) is the contractual milestone at which the construction works are deemed substantially complete and the building is handed over to the client. It triggers retention release and the start of the defects liability period.
Pre-Construction Services Agreement
PCSAA Pre-Construction Services Agreement (PCSA) is a contract between client and contractor covering the contractor's services during the pre-construction phase of a two-stage tender — typically including design input, buildability advice, and target cost development.
Procurement Package
A procurement package is a defined parcel of construction work let to a single sub-contractor or supplier. A typical UK building project has 20–60 packages covering everything from groundworks to floor finishes.
Provisional Sum
PSA provisional sum is an allowance included in the contract sum for work that cannot be fully specified at tender. The actual cost is established later and substituted for the allowance at final account.
R
RIBA Plan of Work
Stages 0–7The RIBA Plan of Work is the UK construction industry's framework for organising the design and delivery of building projects, structured into 8 stages from strategic definition (0) through to use (7).
RIBA Stage 4
Technical DesignRIBA Stage 4 — Technical Design — is the stage at which design is fully resolved, tender documents are prepared, and cost certainty is established before procurement begins.
S
S-Curve
Cashflow S-CurveAn S-curve is a graphical representation of cumulative project spend over time, named for its characteristic S-shape: slow at the start, rapid in the middle, slow at the end.
Snagging
Snagging is the process of identifying minor defects in completed building work — typically just before practical completion — so the contractor can remedy them before the building is handed over to the client.
V
Valuation
Interim valuationA valuation is the monthly assessment of work executed on a construction project, used to certify the contractor's next interim payment. The QS calculates the value of work in place; the certifier issues the payment certificate.
Variation
A variation is a change to the contracted scope of work after the contract has been signed. Under JCT it's a "variation"; under NEC it's a "compensation event". Both adjust cost and programme.
21entries · UK construction commercial & project controls.
Built for the people doing this work.
Projavio is the construction operating system for UK consultancies. Cost reports, cashflow, variations — without the workbook stack.